Construction Starts: CFI IF Tufenkji 鈥 Macdonald Stewart (Macdonald Campus)

Please be advised that 好色TV has mandated Corenov Construction to carry out the following project:聽21-089 鈥 CFI IF Tufenkji 鈥 Macdonald Stewart (Macdonald Campus).

Description:聽Partial renovation of laboratory MS3-025.

Construction start date: June 9th, 2025

Planned construction end date: July, 2025

Work schedule:聽Monday to Friday, 6 a.m. to 3 p.m.

Published: 2 Jun 2025

Construction Starts: Lyman Duff - CFI Ernst

Please be advised that 好色TV has mandated Concept P.V.R. to carry out the following project:聽21-028 - Lyman Duff - CFI Ernst

Description: Renovation of existing laboratories on the 6th and 7th floors to support Dr. Ernst鈥檚 research and CFI equipment.

Construction start date: June 5th 2025

Planned construction end date: June 30th 2026

Published: 27 May 2025

Construction Starts: Wong - CFI JELF Oct 2022, Huberman 鈥 Lab 5270

Please be advised that 好色TV has mandated CORENOV Contractors to carry out the work associated with the project hereafter:聽22-013 Wong - CFI JELF Oct 2022, Huberman - Lab 5270

Description:聽To construct a laser enclosure in Laboratory 5270 and integrate its services with the building鈥檚 existing infrastructure.

Construction start date:聽May 14, 2025

Published: 27 May 2025

Construction Starts: New Residence Hall - Emergency Facade Work and Facade Renovation

Please be advised that 好色TV has mandated St-Denis Thompson Inc to carry out the following project:聽18-103 New Residence Hall - Restoration of Facades 鈥 PHASE 2

Description:聽Complete replacement of block facing on building facades and repair of concrete surfaces.

Construction start date: May 5, 2025

Planned construction end date: End of 2026

Work schedule:

Published: 29 Apr 2025

Construction Starts: Duff, CFI IF 2023, Siegel

Please be advised that 好色TV has mandated CORENOV CONSTRUCTEURS to carry out the following project:聽23-027 Duff, CFI IF 2023, Siegel

Description:聽Renovation of lab 615 including replacement of ceiling tiles, repairs to floors/walls, installation of new lab bench and sink

Construction start date: April 28, 2025

Planned construction end date: End of May 2025

Published: 24 Apr 2025

Construction (Re)Starts: Reconstruction of Upper Main Road - Downtown Campus

Please be advised that, following a winter break, construction work will resume with Ceveco Inc. to carry out the following project:聽19-016 Reconstruction of Upper Main Road, Downtown Campus.

Description:聽Reconstruction of the Upper Main Road, from the Y intersection to the McCall MacBain Arts Building, including underground work.

Construction restart date: March 31, 2025

Published: 31 Mar 2025

Construction Starts: Wong CFI IF 2023 Brochure

Please be advised that 好色TV has mandated J.L Prist to carry out the following project: 23-034 - Wong CFI IF 2023 Brochure

Description:聽Renovation of rooms 2240, 2241, mainly around electrical and mechanical systems.

Construction start date:聽March17, 2025

Planned construction end date:聽July 18, 2025

Published: 26 Feb 2025

Construction Starts: Lot 3 - Corrective Masonry Work on the Corner of the Staircase Wall (MNI Rockefeller Wing)

Please be advised that 好色TV has mandated Atwill-Morin Ma莽onnerie (Groupe Atwill-Morin Inc.) to carry out the following project:聽22-035 (B159) Lot 3 - Corrective masonry work on the corner of the staircase wall (MNI Rockefeller Wing)

Published: 24 Feb 2025

Construction Starts: Currie Gym - Replacement of the Multistack Chiller

Please be advised that 好色TV has mandated Plomberie Charbonneau to carry out the following project:聽23-012 - Currie Gym - Replacement of the multistack chiller

Description:聽Installation of a new main chiller and its integration into the building control system.

Construction start date:聽February 17, 2025

Planned construction end date:聽May 30, 2025

Published: 11 Feb 2025

Construction Starts: Parasitology Building 鈥 JELF Lu and Liu

Please be advised that 好色TV has mandated CORENOV CONSTRUCTEURS to carry out the following project:聽21-007 Parasitology Building 鈥 JELF Lu and Liu

Description:聽Renovation of lab P039 on the first floor of the Parasitology Building.

Construction start date: March 3rd, 2025

Planned construction end date: March 28th, 2025

Published: 6 Feb 2025

Construction Starts: Life Sciences Complex - Shaft Reconstruction (Room 140)

Please be advised that 好色TV has mandated 鈥淧riest Construction-脡lectricit茅鈥 to carry out the following project:聽14-140 Life Sciences Complex 鈥 Shaft Reconstruction at room 140

Description:聽The project involves reconstructing the wall of the mechanical shaft in Room 140 and painting one side of Corridor 1-HALL12.

Construction start date:聽January 27, 2025

Published: 27 Jan 2025

Construction Starts: Raymond 鈥 JELF Dastmalchi (Lot 2)

Please be advised that 好色TV has mandated XO Construction Inc. to carry out the following project:聽21-002 Raymond (Macdonald Campus) 鈥 JELF Dastmalchi (Lot 2)

Description:聽Renovation of room R1-038.

Construction start date: January 2025

Planned construction end date: July 2025

Work schedule: Monday to Friday, 6 a.m. to 3 p.m.

Published: 23 Dec 2024

Construction Start: Pulp & Paper - JELF OCT 2022, Von Sperber

Please be advised that FMAS Operations, Southeast Sector, will carry out the following project:聽22-029 PULP & PAPER - JELF OCT 2022, Von Sperber

Description:聽To carry out electrical works between Lab 202 and existing electrical panel in 2-Hall1

Construction start date:聽November 4, 2024.

Planned construction end date:聽November 30, 2024

Published: 29 Oct 2024

Construction Start: Wong 鈥 Mezzanine renovation

Please be advised that 好色TV has mandated Corenov Constructeurs to carry out the following project:聽22-028 Wong 鈥 Mezzanine renovation

Description:聽Renovations to 3M055 and office 3M030 to create one new lab space.

Construction start date:聽September 2024

Planned construction end date: February 2025

Published: 11 Sep 2024

Construction start: MNI (Neuro) - CFI JELF room 254 renovation

Please be advised that 好色TV has mandated ISI Construction Inc. to carry out the following project:聽23-117 MNI (Neuro) - CFI JELF room 254 renovation

Description:聽Renovation of room 254 (incl. new interior finishes, upgrade of electromechanical services) to accommodate research needs.

Construction start date: September 11, 2024

Planned construction end date: November 15, 2024

Published: 11 Sep 2024